City Manager Presents Proposed 2012-13 Budget

Manager Lehmann Walker gave the council an overview Monday.

 

University City City Manager Lehman Walker presented his proposed 2012-13 budget to the city council Monday.

Walker cautioned council members and those in the audience Monday that this is an initial proposed budget and is subject to change several times before it is finally approved in June.

The projected General Fund budget revenue is $26,168,860. The city's projected expenditures are $25,727,277, for a surplus of $441,583.

Several challenges face the city in its budgeting process. According to the 2010 Census, U City's population declined 5.5 percent from 2000, which leads to a per capita revenue reduction.

The city's sales tax figures have been flat for the past several years and with the current economic conditions, Walker said he didn't anticipate a change in the foreseeable future. 

University City needs to put money into repairing its infrastructure — specifically its roads, sidewalks and curbs. The sidewalks and curbs need to be brought up to ADA (Americans with Disabilities Act) standards. 

"We are an inner ring suburb with aging infrastructure," Walker said. 

For the fourth year in a row, the budget does not include cost of living increases for city employees. There is a 10 percent hike in medical insurance costs.

A quick list of budget components includes:

  • No reduction in city services
  • No increase in real estate taxes
  • No increase in sales tax revenue
  • Increase in funding for police and fire operations
  • Partnership with the School District of University City to share the cost of a dedicated grant writer.
  • Increase in funding for U City in Bloom
  • Funding for City Hall Summer Youth Program.

Capital Improvements for Fiscal Year 2012

Item General Grant Econ. Dev. Fleet
Fire Station #1 $874,494 $2,612,237
Ferguson Bridge Replacement $58,016* $522,143
Loop North Parking Lot
$128,500
Jackson Pedestrian Signal $28,000* $112,000
Sidewalk & Curb Upgrade $60,150* $240,600
Transfer Station Deck Repair $156,000
Street Resurfacing  $350,000
Sidewalks & Curbs $175,000 $13,000
Park Maintenance Building Roof $100,000
Golf Concrete Cart Paths $50,000
Heman Athletic Park Fields $40,000 $80,000
Chamberlain Bridge Replacement $18,400* $73,600
Bicycle Facilities Project $4,000* $16,000
Olive Blvd./Westgate Traffic Signal $30,000* $120,000
Forsyth Blvd/North & South Road Resurfacing $12,500* $49,800
Vehicles and Equipment $1,250,000**
TOTAL CAPITAL $1,956,560 $3,839,380 $128,500 $1,250,000

Editor's note: * Requires grant match. **Purchased from fleet funds set aside for replacement.

The city will hold more meetings and workshops on the budget before the city council votes on the final draft.

Related Topics: Fiscal Year 2012-13, Proposed Budget, lehman walker, and university city

Steve

12:37 pm on Wednesday, February 29, 2012

Does anyone have a link to the actual proposed budget? It is difficult to see how Mr. Walker was able to increase the surplus above last year with increased spending and no increase in revenue.